Listen Live
Power 107.5 Featured Video
CLOSE

American Electric Power has issued a tentative timeline for power restoration based on location. Keep listening to Magic Power 107.5 for further details.

The following times are outside estimates, saying that the work may be completed and power restored sooner.

At this point, restoration is expected to continue for at least 5-7 days for the majority of the customers affected. This is an early estimate that could change if additional damaging weather hits the area.

Initial estimated event restoration times follow. These restoration times will be updated on an ongoing basis as assessment continues and repairs are made. Again, these are early estimates that could change if we experience additional damaging weather.

Estimated restoration times by affected area:

Athens Area

Gallipolis: Midnight July 6

Lancaster: Midnight July 7

Marietta: Midnight July 6

Pomeroy: Midnight July 6

Wellston: Midnight July 10

Canton Area

Coshocton: Midnight July 5

New Philadelphia:   Noon July 1

Chillicothe Area

Chillicothe: Midnight July 5

Chesapeake:  Midnight July 4

Hillsboro: Midnight July 2

Ironton: Midnight July 4

Portsmouth:   Midnight July 5

Columbus Area

Delaware: Midnight July 2

Northeast: Midnight July 7

Northwest: Midnight July 7

Southeast: Midnight July 6

Southwest: Midnight July 3

Newark Area

All areas: Midnight July 8

Ohio Valley Area

Belmont: Midnight July 4

Steubenville: Midnight July 2

Wheeling: Midnight July 6

Western Ohio Area

Bucyrus: Midnight July 3

Findlay: Midnight July 7

Kenton: Midnight July 4

Lima:  Midnight July 7

Ottawa: Midnight July 7

Upper Sandusky:  Midnight July 3

Van Wert: Midnight July 7

RELATED: Mayor Coleman Calls For ‘Operation Cool Down’ in these hot days!